News
Framing almost complete
Framing and windows being installed, on track for lock up towards the end of June or early July.
Framing and windows being installed, on track for lock up towards the end of June or early July.
A slight delay between updates, but don’t take it to mean we haven’t been hard at work! On the contrary, there has been rapid progress with our construction program at Pine Cove. Have a look at the gallery below for some of the things that have happened over the past Read more…
The formwork has been removed from the first floor, leaving lovely, tall ceilings and bright rooms in their place. It has been put to good use together, with the formwork going up to the second floor, ready for pouring the third (and final) floor slab. At this rate, the structure Read more…
Happy new year everyone. Our bricklayers have been hard at work over the Xmas period, laying the blockwork on the second storey. Things are coming along nicely.
Well that was quick. First floor concrete blockwork has been laid, and the next slab is getting ready for pouring.